Protester: Viderity Inc.
Solicitation Number: 140D0426Q0016
Agency: Department of the Interior
File number: B-424422.4
Status: Case Currently Open
Filed Date: Sep 8, 2026
Due Date: Dec 17, 2026
Track Related GAO Activity Here
*Note: The U.S. Department of the Interior may act as an acquisition partner on behalf of other federal agencies for certain procurements.
Updated September 1, 2026
The court sided with Viderity in their pursuit of cost reimbursement in this case. See more below.
DIGEST
Reimbursement of costs of filing and pursuing protest allegation that an agency evaluator had an apparent personal conflict of interest is recommended where the agency unduly delayed taking corrective action in the face of clearly meritorious protest ground because a reasonable agency inquiry into the initial protest allegations would have revealed facts disclosing the absence of a defensible legal position.
DECISION
Viderity Inc., a small business of Leesburg, Virginia, requests that our Office recommend that it be reimbursed for the costs associated with filing and pursuing its protest (B-424422; B-424422.2; B-424422.3), challenging the issuance of an order to Bixal Solutions Inc., a small business of Fairfax, Virginia, under request for quotations (RFQ) No. 140D0426Q0016, issued by the Department of the Interior (DOI), on behalf of the Department of Health and Human Services (HHS), for communications infrastructure support. The protester argues the protest was clearly meritorious and the agency failed to take timely corrective action in response.
We grant the request.

The agency is performing an internal investigation as part of a corrective action before determining award